Kin Beach Pump Station

Our civil work included steep-slope watermain construction, drainage, traffic management and restoration.

Project information

A closer look at our work.

We delivered civil work for the Kin Beach Pump Station in a steep corridor beside a public roadway and homes.

Location
Vernon, BC
Work undertaken
April–October 2025
About 465 m600 mm ductile iron watermain
About 550 m500 mm HDPE watermain
About 90 mstormwater culvert

Our scope

  • Completed trenching, rock excavation, grading and engineered pipe anchoring on steep slopes.
  • Installed watermains and stormwater culvert.
  • Coordinated traffic control and detours, then reinstated pavement, concrete and landscaping.