Farleigh Lake Dam Upgrade

Our dam rehabilitation scope included water-control works, sheet piling and gabion installation.

Project information

A closer look at our work.

As prime contractor, we completed dam improvements and water-control work for the Penticton Indian Band.

Client
Penticton Indian Band
Our role
Prime contractor
Work undertaken
August–December 2022

Our scope

  • Completed earthworks and raised the earthen dam by approximately one metre.
  • Installed riprap, a culvert, sheet piles and gabion protection.
  • Completed spillway and outlet works with dewatering and cofferdam measures.